Decision details

A6210/A657 Rodley Roundabout Improvement

Reference: D41138

Decision Maker: Executive Board

Decision status: Recommendations Approved (subject to call-in)

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To approve the replacement of the existing roundabout with a signalised gyratory and associated pedestrian, cycling and public transport improvements.

 

To approve the implementation of the scheme and to give authority to incur expenditure of £3,475,000: comprising £2,432,000 DfT Pinch Point funding; £731,761 developer funding and £311,239 from the LTP 2014/15

Decisions:

The Director of City Development submitted a report detailing the total scheme costs of £3,475,000 for the Rodley Roundabout improvements initiative. In addition, the report sought authority to incur such expenditure and also sought approval to invite tenders and to implement the proposed highway improvement works to the roundabout.

 

The Board welcomed the proposals to improve the A6120/A657 Rodley Roundabout, with specific reference being made to the benefit which would be gained from the provision of controlled pedestrian crossing facilities.

 

In highlighting the work which was also scheduled to take place to improve A65/A6012 Horsforth roundabout and also the A647/B6154 Thornbury Barracks junction, Members noted that the cumulative impact of such works would be monitored, and that every effort would be made to ensure that any disruption was minimised.

 

RESOLVED –

(a)  That the construction of the Council’s scheme to fully signalise Rodley Roundabout with associated highway works, at an estimated cost of£3,475,000, be approved.

 

(b)  That approval be given to inject £3,475,000 into the City Development capital programme.

 

(c)  That authority be given to incur expenditure of £3,475,000 (comprising of works costs £3,202,375 and staff fee costs £272,625) funded from a Department for Transport Tranche 4 Local Pinch Point Fund Government grant of £2,432,000, a Local Transport Plan grant of £306,239, and a Private Developer section 106 receipt of £736,761.

 

(d)  That it be noted that the officer responsible for implementing these proposals is the Acting Head of Transport Policy and that the works would be procured through appropriate tender procedures and delivered in line with the dates identified in section 4.7 of the submitted report.

 

(e)  That it be noted that it is proposed to deliver the proposals contained within the submitted report with the already approved proposals for Horsforth Roundabout as a single contract.

 

Reason Key: Expenditure > £250,000;

Wards Affected: Calverley and Farsley;

Portfolio Holder: Development and the Economy

Other reasons / organisations consulted

Email and letter drop

Consultees

Executive Member for Development and the Economy

 

Ward Members

 

Residents

 

Businesses

 

Emergency Services

 

Metro

Contact: Paul Russell, Principal Engineer 0113 2476171 Email: paul.russell@leeds.gov.uk.

Report author: Paul Russell

Publication date: 23/04/2014

Date of decision: 02/04/2014

Decided at meeting: 02/04/2014 - Executive Board

Date comes into force if not called in: 12/04/2014

Call-in deadline date: 11/04/2014

Accompanying Documents: