Decision details

South Bank Regeneration

Reference: D42565

Decision Maker: Executive Board

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Further to a range of decisions made by Executive Board in the last eighteen months on regeneration of the South Bank, Executive Board is asked to agree actions to facilitate further regeneration and growth across the South Bank of the City Centre.

Decisions:

Further to Minute No. 118, 19th November 2014, the Director of City Development submitted a report providing an update on the progress being made to regenerate the South Bank area of the city centre and to obtain approval to short term actions which would facilitate further growth and regeneration.

 

Members welcomed the contents of the submitted report and highlighted the significant potential and opportunities for the city and the wider area which lay in the regeneration of the South Bank.

 

Following consideration of Appendix 1 to the submitted report, designated as exempt from publication under the provisions of Access to Information Procedure Rule 10.4(3), which was considered in private at the conclusion of the meeting, it was

 

RESOLVED –

(a)  That the progress being made in regeneration initiatives across the South Bank be noted, and that the priorities, as set out in section 3 of the submitted report be agreed;

 

(b)  That the Board re-affirms that securing funding to support the restoration of Temple Works is a priority for the city given its at-risk status, and that it be requested that officers continue to work with third parties to facilitate its restoration.

 

(c)  That a report be submitted to Executive Board with proposals to invest in the public realm and spaces across the South Bank;

 

(d)  That a report be submitted to Executive Board by Autumn 2015 with proposals to facilitate regeneration along the Hunslet Riverside;

 

(e)  That the Chief Officer Economy and Regeneration be requested to explore the feasibility of the Council’s City Centre Management function providing urban management support across the South Bank area;

 

(f)  That approval be given to the recommendations as set out in paragraphs 6.0, 6.1 and 6.2 of the submitted exempt appendix 1 concerning potential future land assembly proposals;

 

(g)  That it be noted that the Chief Officer Economy and Regeneration will be responsible for the implementation of such matters.

 

(The Council’s Executive and Decision Making Procedure Rules state that a decision may be declared as being exempt from Call In if it is considered that any delay would seriously prejudice the Council’s or the public’s interests. As such, it was determined that the resolutions relating to this report were exempt from the Call In process as they were time-bound and would not be properly exercised if were called in)

Reason Key: Affects more than 1 ward;

Wards Affected: City and Hunslet;

Portfolio Holder: Executive Member for Regeneration, Transport and Planning

Other reasons / organisations consulted

Consultation with Executive Member

Consultees

Executive Member for Regeneration, Transport and Planning.

Contact: Lee Arnell, Principal Regeneration Officer 0113 2475408 Email: lee.arnell@leeds.gov.uk.

Report author: Lee Arnell

Publication date: 24/07/2015

Date of decision: 15/07/2015

Decided at meeting: 15/07/2015 - Executive Board

Effective from: 25/07/2015