Decision details

Harehills Primary School - Provision of Additional Classrooms

Reference: D32443

Decision Maker: Executive Board

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

Approval to incur capital expenditure in respect of the scheme to provide additional accommodation over a two year period at Harehills Primary School.

Decisions:

The Chief Executive of Education Leeds submitted a report on a proposed scheme to provide additional accommodation at Harehills Primary School.

 

RESOLVED –

(a)  That the design proposals for additional accommodation at Harehills Primary School be approved.

(b)  That expenditure of £579,700 from capital scheme 13286 be authorised.

 

Wards Affected: Gipton and Harehills;

Portfolio Holder: Portfolio: Children's Services

Contact: Chief Executive of Education Leeds.

Publication date: 16/03/2007

Date of decision: 14/03/2007

Decided at meeting: 14/03/2007 - Executive Board