Residual Waste Treatment Project - approval to proceed to the next stage of the procurement and approve the short list of bidders

Reference: D35435

Decision Maker: Deputy Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Under the powers delegated to me by Executive Board under PPP/PFI governance arrangements and further to the Executive Board decisions taken on 16 July and 05 November 2008 and a meeting of the Residual Waste Treatment Project Board on 16 April 2009 that considered the Project Board Report dated 16 April 2009 along with appendices, I Dave Page Deputy Chief Executive with the concurrence of at least two other members of Project Board hereby approve:

i.) the results of the ISOS evaluation process;
ii.) the recommendation that no Bidder should be disqualified on the basis of a score of four or below on a single criteria or sub criteria
iii.) that four Bidders are taken forward to the next stage of the procurement process and
iv.) that the Bidders which are to progress to the next bid stage are as follows:
• Aire Valley Environmental;
• MVV Umwelt GmbH;
• Veolia ES Aurora Ltd;
• United Utilities.

This is a significant operational decision and is therefore not eligible for call in. This is because this decision is putting into effect a previous key decision taken by Executive Board on 16 July 2008 namely that officers be authorised to begin procurement of this project through placement of OJEU and other appropriate contract notices.

Further information regarding the Bidders to progress to the next stage is attached at Appendix 1.

Wards Affected: (All Wards);

Advice Sought: Finance; Legal;

Contact: Andrew Tate - 07891 271746.

Publication date: 20/05/2009

Date of decision: 18/05/2009