Decision details

City Connect Cycle Parking Scheme Capital Scheme Number : 32017 / 000 / 000

Reference: D41031

Decision Maker: Director of City Development

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Chief Officer of Highways and Transportation:
i) noted the contents of this report;
ii) approved the supply of 16 Car Bike Ports at a cost of £64,974
iii) approved installation and supply of Sheffield Stands and installation of Car Bike Ports, by Leeds City Council’s own Highways Maintenance Team, at the locations shown on drawings CC-716969-CCCP-01, 02 and 03 included in Appendix A and in Appendix C at cost of £36,560; and
iv) gave authority to incur total expenditure of £106,534, comprising £101,534 works costs ( as detailed above ), and £5,000 internal staff fee costs, fully funded from the LTP Transport Policy Capital Programme.

Wards Affected: City and Hunslet;

Contact: Mark Robinson, Cycling Officer 0113 3951470 Email: mark.robinson@leeds.gov.uk.

Publication date: 31/03/2014

Accompanying Documents: