Reference: D41125
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Head of Engineering Services:
i) noted the principle of the highway works as outlined in Section
3.1 and indicated on drawings referenced: DC/SF/TDS00499/01 and
land dedication plan DC/SF/TDS00499/02;
ii) gave authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980, whereby the works associated with the
development are carried out by this Council at the cost of the
developer;
iii) gave authority to implement the works as set out in Section
3.1;
iv) approved an injection of £114,000 into the City
Development Capital Programme, to be fully funded by the developer
under a Section 278 agreement;
v) gave authority to incur expenditure of £114,000, being
£95,000 works costs and £19,000 staff costs, to be
fully funded by the developer under a Section 278 agreement;
vi) gave authority to advertise a notice under the provisions of
Section 23 of the Road Traffic Regulation Act 1984 notifying of the
proposed pedestrian crossing facilities;
vii) approved the proposed amendments to the existing waiting
restrictions as described in 3.1.3 on Cudbear Street and Sheaf
Street; and
viii) instructed the City Solicitor to advertise a draft Traffic
Regulation Order, and, if no valid objections are received, to
make, seal and implement the Order as advertised.
Wards Affected: City and Hunslet;
Contact: Steve Flanagan, Highways Officer 0113 24 75906 Email: steve.flanagan@leeds.gov.uk.
Publication date: 17/04/2014
Accompanying Documents: