Decision:
The Built Environment Programme Manager
1. Authorised expenditure of £180,721 from capital scheme
number 16585/BGE/HCR to enable the proposed works at Hunslet Carr
Primary School.
2. Noted the programme dates identified in section 4.2 of this
report in relation to the implementation of this decision. The
final delivery date for this scheme is September 2014.
Wards Affected: City and Hunslet;
Contact: Edward Staveley, Principal Asset Management Officer , City Development 07891271059 Email: edward.staveley@leeds.gov.uk.
Publication date: 10/07/2014