Reference: D41763
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation):
i) noted the contents of this report;
ii) approved the proposals at the total cost of £216,000;
and
iii) gave authority to incur expenditure of £202,000 works
costs and £14,000 staff costs, to be funded from the LTP
Transport Policy Capital Programme.
Wards Affected: Various;
Contact: Andrew Bradley, Senior Engineer 0113 2476785 Email: andrew.bradley@leeds.gov.uk.
Publication date: 31/10/2014