Reference: D41844
Decision Maker: Deputy Chief Executive
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Deputy Chief Executive is requested to
approve an injection of £157,600 into the capital programme
in order to effect the partial refurbishment of the fourth floor of
the West Gate Building and the co-location of 181 staff from
Customer Access, Childrens Services, Adult Social Care, West
Yorkshire Police and Public Health from the Ground Floor of this
building and third floor Great George Street.
The project will also provide furniture and ICT equipment on the
4th floor of West Gate which will be procured from the Changing the
Workplace Programme budget to the sum of £149,700. The Deputy
Chief Executive is requested to give Authority to Spend of
£307,300 for the full amount of both the £157,600 sum
injected and the contribution of £149,700 from the Changing
the Workplace capital programme budget.
Contact: Wendy Allinson, Email: Citizens@Leeds Development Team Lead 07891 271298 Email: wendy.allinson@leeds.gov.uk.
Publication date: 01/12/2014