Reference: D42001
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation):
i) noted the highway works as outlined in Section 3.1 and indicated
on Leeds City Council Drawing Number EP/716988/01/01 at an
estimated cost of £152,650;
ii) gave authority to negotiate the terms of and enter into an
agreement with the landowner/developer under the provisions of
Section 278 of the Highways Act 1980; whereby the works associated
with the development are carried out by this Council at the cost of
the developer; subject to conditions precedent matters (associated
with the planning permission), land ownership and landowner
approval issues being fully resolved;
iii) gave authority to implement the works as set out in Section
3.1, subject to the approval of any necessary planning conditions
and the negotiation of an acceptable Section 278 Legal
Agreement;
iv) approved an injection of £152,650 into the City
Development Capital Programme; and
v) gave authority to incur expenditure of £128,291 works
costs and £24,359 staff costs, to be fully funded by a
developer per a Section 278 legal agreement.
Wards Affected: Garforth and Swillington; Harewood; Kippax and Methley;
Contact: Neil Chamberlain, Highways Officer 0113 2475288 Email: neil.chamberlain@leeds.gov.uk.
Publication date: 27/01/2015