Reference: D42013
Decision Maker: Director of Environment and Housing
Is Key decision?: Yes
Is subject to call in?: Yes
Seeking authority to spend £2.025m on replacement bins for the period up to 2017/18
The Director of Environment and Housing agreed to note the content of this report and;
provide the authority to spend £365.7k on the existing bin replacement scheme (12594).
provide the approval to the bringing forward of spend planned for 2015/16 into 2014/15 of £300k
provide the authority to spend on the new replacement scheme of £2,025k (to the year 2017/18) including £165k on Street Litter bins
Note that a further injection into the capital programme of around approximately £5.9m will be required for the period late 2017/18 to 2024/25. This is expected to be completed on an annual basis by injecting around £750k to £800k in the February capital programme updates
Reason Key: Expenditure > £250,000;
Wards Affected: (All Wards);
Other reasons / organisations consulted
Executive Board Member, Director E&H, Chief Officer Waste, Chief Officer Environmental Action, Finance
Consultees
Neil Evans, Susan Upton, Helen Freeman, Kevin Mulvaney, Councillor M Dobson
Contact: Elizabeth Behrens, Strategy & Development Manager 0113 2475980 Email: Liz.Behrens@leeds.gov.uk.
Publication date: 30/01/2015
Date of decision: 09/02/2015
Effective from: 17/02/2015