Reference: D42204
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
1. The Chief Officer (Highways and
Transportation):
i) Granted consent under section 23 of the Land Drainage Act, 1991,
as amended by the Floods and Water Management Act, 2010 to the
proposed diversion as outlined in the application by Haigh
Huddleston & Associates Ltd and dated 6 January, 2015;
ii) Approved the following conditions, which will be attached to
any consent:
a) The works on site should be carried out in accordance with that
proposed in the Method Statements submitted by Haigh Huddleston
& Associates Ltd, dated January 2015;
b) On completion of the garages of plot 10/ 11 and the house of
plot 11, the section of the diverted culvert between Manholes S3 up
to S5 must be surveyed to determine the state of the culvert. The
survey report must be submitted to the council/ FRM section and any
necessary remedial works determined by the survey must be completed
to the satisfaction of the council;
c) The works shall be commenced within 12 months of the date of the
approval. Should the works not be commenced within this timeframe,
the applicant will need to re-apply for consent; and
d) The applicant shall provide 7 days’ notice to LCC (Flood
Risk Management Section (FRM)) of their intention to commence the
works.
Wards Affected: Calverley and Farsley;
Contact: Magda Lezama, Highways & Transportation Officer 011 2478784 Email: magda.lezama@leeds.gov.uk.
Publication date: 26/03/2015