Reference: D42593
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation):
i) approved the undertaking of the implementation of a scheme to
improve the capacity of, and reduce congestion, at the roundabouts
links at junctions 27 & 28 of the M62, as indicated on the
attached drawing numbers B2005501/J27/100/002 &
B2005501/J28/100/001; and
ii) entered into an agreement under the provisions of Section 4 of
the Highways Act 1980 (attached at appendix A) to allow HE and
their contractor to undertake the works, as specified above, on
LCC’s network.
Wards Affected: Ardsley and Robin Hood; Morley North; Morley South;
Contact: Paul Foster, Transport Projects Manager 0113 2475392 Email: paul.foster@leeds.gov.uk.
Publication date: 28/07/2015
Accompanying Documents: