The Head of Engineering Services:
i) noted the highway works as outlined in Section 3.3 and indicated
on drawings WB/RL/003 Rev B and S106 Highway Works Plan attached at
Appendix 1;
ii) gave authority to implement the works as set out in Section
3.3; and
iii) gave authority to incur expenditure of £400,000, being
£330,000 works costs and £70,000 staff costs, all to be
fully funded by the developer from the signed S106 Agreement.
Wards Affected: Beeston and Holbeck; Farnley and Wortley;
Contact: Michael Norcliffe, Highways Officer 0113 247 5317 Email: michael.norcliffe@leeds.gov.uk.
Publication date: 07/08/2015