Reference: D42960
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation) is requested to:
i) Grant consent for the proposed works as required under Schedule
2 of the Flood and Water Management Act 2010 which transfers
approvals for works affecting an ordinary watercourse from the
Environment Agency to the Lead Local Authority (LCC).
ii) Approve the following conditions, which will be included with
any consent:
a) The works shall be carried out in accordance with the approved
drawings: FRM/10127/ CON/005 & 006 - General Arrangements,
Sheets 1 & 2 of 2. FRM/10127/ CON/010 & 011- Proposed Silt
Trap Details, Sheets 1 & 2 of 2. FRM/10127/ CON/012 –
Gravel Filter Drainage Details. Any amendments to the approved
drawings will be subject to approval by Council’s Flood Risk
Management (FRM) section;
b) The works shall not commence until a construction method
statement has been submitted to and approved in writing by
FRM.
c) The works shall not be carried out until the further Bat and
Reptile Survey suggested by the Mouchel Ecology Phase one survey
has been carried out and all precautions or necessary provisions
recommended by both the phase one and the additional survey have
been implemented or undertaken to the satisfaction of the council/
Natural Environment team.
d) The works shall be commenced within 3 years of the date of the
approval. Should the works not be commenced within this time frame,
the current approval will be deemed to have lapsed.
e) The applicant shall provide 7 days notice to FRM of their
intention to commence the works; and
f) Final, as-built, drawings shall be submitted to FRM on
completion of the works.
Wards Affected: Garforth and Swillington;
Contact: Magda Lezama, Highways & Transportation Officer 0113 2478784 Email: magda.lezama@leeds.gov.uk.
Publication date: 09/12/2015
Accompanying Documents: