Design & Cost report for phase 1 of Roundhay Secondary School Learning Places Project, capital scheme number 32450/ROU/PH1

Reference: D43096

Decision Maker: Director of Children's Services

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

The Director of Children’s Services is requested to approve the recommendations of the design and cost report to deliver phase 1 of Roundhay Secondary School expansion as part of the Learning Places Programme.

Decision:

The Director of Children’s Services agreed to:

·  Approve the design and cost report for phase 1 of the scheme at Roundhay Secondary School, the cost being £1.6m; with the appropriate details of the programme, design and cost as set out in the attached report; and

·  Note that the Chief Officer, Projects, Programmes & Procurement Unit (PPPU) is responsible for scheme delivery which will be completed by September 2017.

Reason Key: Expenditure > £250,000;

Wards Affected: Roundhay;

Other reasons / organisations consulted

Public consultation period to be completed in November 2015.

Consultees

Schools, public, elected members, local community groups.

Contact: Stephen Grundy 07891 276132 Email: stephen.grundy@leeds.gov.uk.

Publication date: 02/02/2016

Date of decision: 10/02/2016

Effective from: 18/02/2016

Accompanying Documents: