Decision details

Design & Cost Report for the Learning Places Phase 2 2015 Bulge Cohort Hall Extension - Highfield Primary School

Reference: D43347

Decision Maker: Director of Children's Services

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Authority to spend £420,000 to extend the school hall to comply with BB99 regulations as the school has taken a bulge cohort.

Decision:

The Head of Service, Learning Systems agreed to:

·  authorise expenditure of £396,985.65 from capital scheme number 32274/BGE/HIG to enable the extension of the school hall, including any necessary ancillary works, at Highfield Primary School;

·  note the programme dates identified in section 3.5.1 of this report in relation to the implementation of this decision. The final delivery date for this scheme is prior to the commencement of the autumn term in September 2016; and

·  note that the officer responsible for implementation in the Built Environment Project Officer.

Reason Key: Expenditure > £250,000;

Wards Affected: (All Wards);

Other reasons / organisations consulted

None required

Contact: Cindy Costigan, Project Manager, Children's Services 0113 3951080 Email: cindy.costigan@leeds.gov.uk.

Publication date: 27/04/2016

Date of decision: 06/05/2016

Effective from: 14/05/2016