The Built Environment Programme Manager agreed
to:
* authorise expenditure of £50,000 from Capital Scheme Number
32274/BGE/EAR to underwrite the design fees incurred by the chosen
contractor from the YORbuild 2 Framework (Clugston). The design
process will inform the required modular solution prior to the 2016
bulge cohort modular accommodation;
*note the programme dates identified in section 4.2 of this report
in relation to the implementation of this decision. The final
delivery date for this scheme is prior to the commencement of the
September term 2016; and
* note that the officer responsible for impleemtation is the Built
Environment Project Officer.
Wards Affected: City and Hunslet; Gipton and Harehills; Middleton Park;
Contact: Edward Staveley, Principal Asset Management Officer , City Development 0113 2475351 Email: edward.staveley@leeds.gov.uk.
Publication date: 06/05/2016