Decision details

Authority to enter into a Pre-Construction Agreement with the Stage 1 appointee for the procurement and delivery of temporary accommodation at a number of Leeds Primary Schools

Reference: D43364

Decision Maker: Director of Children's Services

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

The Built Environment Programme Manager has approved:
* entry into a Pre-Construction Agreement with Clugston Construction Ltd to develop designs relating to the installation of modular accommodation on 9 Primary Schools with a liability up to a maximum of £75,000 for bid, design and Building Control fees should the Council decide to cancel all of the schemes prior to signing construction contracts and a liability up to a maximum of £85,000 to pay for required site surveys; and
* underwriting the potential expenditure up to a maximum of £75,000 to cover the liability should the Council cancel all 9 schemes and up to a maximum of £85,000 to pay for required site surveys.

Wards Affected: (All Wards);

Contact: Craig Taylor, Programme Manager 07891 276597 Email: craig.taylor@leeds.gov.uk.

Publication date: 06/05/2016

Accompanying Documents: