Reference: D43484
Decision Maker: Director of Children's Services
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Programme Manager, Built Environment
agreed to:
* authorise expenditure of £239,299 from capital scheme
number 32274/BGE/HOV to underwrite a proportion of the parts,
materials and manufacture costs associated with the production of
modular accommodation to support the bulge cohort scheme procured
through the YORbuild 2 framework. The underwriting of these costs
will secure the vital manufacturing slot required for the
production of the modular accommodation to enable delivery for the
start of the September term 2016.
* note the programme dates identified in section 4.2 of the
attached report in relation tot he implementation of this decision.
The final delivery date for this scheme, subject to contract, is
prior to the commencement of the September term 2016.
* note that the officer responsible for implementation is the Built
Environment Project Officer.
Wards Affected: Gipton and Harehills;
Contact: Edward Staveley, Principal Asset Management Officer , City Development 0113 2475351 Email: edward.staveley@leeds.gov.uk.