Design & Cost Report for the Learning Places 2016 Bulge Cohort - St Augustine Catholic Primary. Capital Scheme Number: 32274/BGE/AUM

Reference: D43541

Decision Maker: Director of Children's Services

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

To authorise the expenditure of approximately £350k (final cost estimate awaited, will be included within the content of the scheme specific DCR) to facilitate the supply of modular classroom buildings at St Augustine’s Catholic Primary School. This is required to fulfil the aims of the Learning Places Programme, necessary to ensure sufficient pupil places effective from September 2016. The budget estimate quoted includes all necessary construction works to facilitate this project, professional design fees, professional surveys and any necessary decant required to facilitate a late August 2016 occupation. St Augustine’s Catholic Primary School has been identified as the epicentre of projected pupil place demand within the Gipton & Harehills ward.

Decision:

The Head of Service, Learning Systems agreed to:

·  Authorise expenditure of £460, 783 from capital scheme number 32274/BGE/AUM to enable the installation of essential accommodation, including any necessary ancillary works, at St Augustine Catholic Primary School;

·  Note that the figure detailed above includes £73,940 of underwriting costs approved under a previous design cost report;

·  Note the programme dates identified in section 4.0 of the attached report in relation to the implementation of the decision. The final delivery date for this scheme is prior to the commencement of term September 2016; and

·  Note that the officer responsible for implementation in the Built Environment Principal Development Officer.

Reason Key: Expenditure > £250,000;

Wards Affected: Gipton and Harehills;

If exempt from Call-In, the reason why Call-In would prejudice the interests of the Council or the public:: If the decision is not implemented before the end of the call-in period on 20th July, there is a significant risk that the project will not be completed in time for the start of term, with the subsequent risk of disruption to the education of the children starting at St Augustine Catholic Primary School this year.

Other reasons / organisations consulted

Consultation has been on-going with the school management team, LCC Highways & LCC Planning Department. Ward member briefings are being issued periodically at key points in the project programme.

Consultees

LCC Highways

LCC Planning Department

St Augustine’s Catholic Primary management team

St Augustine’s Catholic Primary School Governors

Contact: Nigel Wilson, Senior Contract Manager 07891 271056 Email: nigel.wilson@leeds.gov.uk.

Publication date: 06/07/2016

Date of decision: 14/07/2016