Decision details

Design & Cost Report & Tender Acceptance for the Learning Places 2016 Bulge Cohort – Bramley Primary School Capital Scheme Number: 32274/BGE/BRM

Reference: D43646

Decision Maker: Director of Children's Services

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

The Built Environment Programme Manager agreed to:

•Authorise expenditure of £221,552 from capital scheme number 32274/BGE/BRM to enable orders to be placed for furniture for the identified schools within the Learning Places 2016 Bulge Cohort Programme.

•Authorise acceptance of the tender submitted by Leeds Building Services in the sum of £172,748. This figure is purely the construction work and is exclusive of NPS design development costs.

•Note the programme dates identified in section 4.0 of this report in relation to the implementation of this decision. The final delivery date for this scheme is prior to the commencement of term September 2016.

•Note that the officer responsible for implementation is the Built Environment Principal Development Officer.

Wards Affected: Bramley and Stanningley;

Contact: Christopher Gosling, Estate Management - Development Officer 0113 39 51403 Email: christopher.gosling@leeds.gov.uk.

Publication date: 18/08/2016