Reference: D43693
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Head of Transportation:
i) Noted and approved the contents of this report;
ii) Approved the implementation of the scheme as detailed on
Drawing No. HDC/995819/01/01b; and
iii) Approved the injection of £693,000 into the LCC Highways
and Transportation Capital Plan.
iv) Gave authority to incur expenditure of £693,000, being
£650,800 works costs and £42,200 staff fees, fully
funded by external income from WYCA.
Wards Affected: City and Hunslet;
Contact: David Worton, Senior Engineer 0113 2243723 Email: david.worton@leeds.gov.uk.
Publication date: 02/09/2016
Accompanying Documents: