The Director of Children's Services agreed
to:
1. note that the two stage process with the original contractor has
been abandoned due to failure on their part to submit an affordable
scheme based on the original design proposals and also a revised
contractor-led design at Gateway 1 of the revised scheme.
2. approve a revised procurement stragtegy, allowing the Councils
Strategic Partner - Leeds LEP Limited, to be commissioned to
deliver the expansion to Hollybush Primary School as it cannot be
delivered by the Internal Provider or through an existing Framework
Agrrement, by December 2017.
3. approve the wiaver of the following Contracts Procedure Rules to
enable the delivery of essential accommodation at Hollybush Primary
School:
* CPR 9.1 - Where no appropriate internal provider, Exclusive
Supplier, existing provider, LCC Approved Framework Agreement or
Approved Framework Agreement exists, competition is required for
procurements valued over £100k.
* CPR 9.2 - Where there are suficient numbers of providers at least
four written tenders will be invited.