Reference: D43866
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation):
i) Noted the contents of this report;
ii) Approved the detailed design and implementation of the package
of works as detailed in section three of this report and shown in
drawing TM-22-2409-GA-0;
iii) Gave authority to incur expenditure of £245,000,
compromising of £220,000 works cost and £20,000 staff
fees and £5,000 legal fees, all to be funded from the LTP
Transport Policy Capital Programme; and
iv) Approved with reference to the powers contained in Section
66(4) of the Highways Act 1980, that the relevant lengths of
footway and carriageway as proposed cycle tracks are removed and
that following the removal of the footways, cycle tracks are
constructed under the powers contained under the provisions of
section 65(1) of the Highways Act 1980 for shared joint use by
pedal cyclists and pedestrians.