Shakespeare Primary School Expansion - Design and Cost Report

Reference: D44046

Decision Maker: Director of Children's Services

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Request for authority to spend to create 315 additional pupil places through the expansion and relocation of Shakespeare Primary School.

The decision is a Key Decision because it will be greater than £250k.

 

Decision:

The Director of Children’s Services agreed to:

 

·  Approve the design and cost report for the scheme to expand and relocate Shakespeare Primary School, the cost being £11,585,080 with the appropriate details of the programme, design and cost report as set out in this report; and

 

·  Note that the Chief Officer, Projects, Programmes and Procurement Unit id responsible for scheme delivery which is scheduled for completion by September 2018.

Reason Key: Expenditure > £250,000;

Wards Affected: Burmantofts and Richmond Hill; Gipton and Harehills;

Other reasons / organisations consulted

Public consultation to be undertaken prior to planning submission and through the project lifecycle

Consultees

School, early years providers, public, elected members, local community groups

Contact: Jacqueline Robertson, Project Manager 0113 3785915 Email: jacqueline.robertson@leeds.gov.uk.

Publication date: 13/01/2017

Date of decision: 23/01/2017

Effective from: 31/01/2017