Reference: D44146
Decision Maker: Director of City Development
Is Key decision?: Yes
Is subject to call in?: Yes
Chief Officer of Highways and Transportation toapprove the detailed design, implementation and expenditure associated to the proposal made in the report as the basis for the 2016/17 programme for the introduction of a ‘Super’ crossing and alterations to Leeds Bus Station by providing a new egress.
The Chief Officer (Highways and Transportation):
i) Noted the contents of this report;
ii) Gave authority to design and implement the scheme as detailed on Drawing No. TM-10-2496-GA-01a at a total cost of £460,000;
iii) Gave authority to incur the expenditure of £76,000 staff, design and supervision costs, and £384,000 Works costs, partly funded from the Local Transport Plan Transport Policy Capital Programme and the Leeds Transport Investment Capital Programme; and
iv) Requested the City Solicitor to:
a) Progress the dedication of land from West Yorkshire Combined Authority to become part of Leeds City Council’s publicly adopted and maintained highway.
Reason Key: Expenditure > £250,000;
Wards Affected: City and Hunslet;
Other reasons / organisations consulted
Ward Members have been consulted via email. Officers have also been liaising regularly with other stakeholders.
Consultees
Ward Members, emergency services, West Yorkshire Combined Authority, bus operators (First & Arriva), National Express & Cycle Forum
Contact: David O'Donoghue 0113 3787500.
Publication date: 20/02/2017
Date of decision: 06/03/2017
Effective from: 14/03/2017