Decision details
Design & Cost Report for the 'Early Works' required to facilitate the Learning Places expansion of Bramley Primary School Capital Scheme Number: 32450/BRA/000
Reference: D44225
Decision Maker: Director of Children's Services
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Decision:
The Head of Service Learning Systems agreed
to:
1.Sanction the requirement to enter into an ‘Early Works
Agreement’ with the LLEP for ICL to deliver a package of
works to facilitate the Learning Places expansion at Bramley
Primary School. This will take the form of an ‘Early
Works’ agreement between the authority and Leeds D&B One
Ltd for the sum of £249,000.
2.Approve the expenditure of £249,000 from capital scheme
number 32450/BRA/000 for the completion of a package of
‘Early Works’ necessary to deliver the expansion of
Bramley Primary School for a September 2017 occupation. This is to
be funded from the £3.25m allocated for the full expansion of
Bramley Primary as part of the Learning Places Programme report
approved at the December 2016 Executive Board.
3.Note the programme dates identified in section 4.0 of this
report, in relation to the implementation of this decision,
represents the critical path for project success and must be
adhered to where possible.
4.Note that a separate DCR will be submitted for the main works
once financial close has been achieved in March 2017.
5.Note that the officer responsible for implementation is the Head
of Service Learning Systems.
Wards Affected: Bramley and Stanningley;
Contact: Christopher Gosling, Estate Management - Development Officer 0113 3951403 Email: christopher.gosling@leeds.gov.uk.
Publication date: 17/03/2017