Design & Cost Report for the 'Early Works' required to facilitate the Learning Places expansion of Bramley Primary School Capital Scheme Number: 32450/BRA/000

Reference: D44225

Decision Maker: Director of Children's Services

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

The Head of Service Learning Systems agreed to:

1.Sanction the requirement to enter into an ‘Early Works Agreement’ with the LLEP for ICL to deliver a package of works to facilitate the Learning Places expansion at Bramley Primary School. This will take the form of an ‘Early Works’ agreement between the authority and Leeds D&B One Ltd for the sum of £249,000.

2.Approve the expenditure of £249,000 from capital scheme number 32450/BRA/000 for the completion of a package of ‘Early Works’ necessary to deliver the expansion of Bramley Primary School for a September 2017 occupation. This is to be funded from the £3.25m allocated for the full expansion of Bramley Primary as part of the Learning Places Programme report approved at the December 2016 Executive Board.

3.Note the programme dates identified in section 4.0 of this report, in relation to the implementation of this decision, represents the critical path for project success and must be adhered to where possible.

4.Note that a separate DCR will be submitted for the main works once financial close has been achieved in March 2017.

5.Note that the officer responsible for implementation is the Head of Service Learning Systems.

Wards Affected: Bramley and Stanningley;

Contact: Christopher Gosling, Estate Management - Development Officer 0113 3951403 Email: christopher.gosling@leeds.gov.uk.

Publication date: 17/03/2017