The Director of Children & Families agreed
to:
1. Authorise expenditure of £1,179,305 from capital scheme
number 32450/BRU/PH1 to deliver the main works package required to
facilitate the conversion of the former Brudenell Centre College
building into useable teaching accommodation. The works detailed
herein are required to facilitate the first phase of this
conversion which refurbishes the newly acquired, former college
owned section of the facility.
2. Authorise acceptance of the tender submitted by Leeds Building
Services in the sum of £938,833.55. This figure is purely the
construction work and is exclusive of ancillary costs including the
previously approved package of enabling works.
3. Note the programme dates identified in section 4.0 of this
report in relation to the implementation of this decision. The
final delivery date for this scheme is prior to the commencement of
term September 2017.
4. Note that the officer responsible for implementation is the
Built Environment Project Officer.
5. Note that the approval sum detailed under point 1 above includes
the following elements:
a. £938,833.55 for constructions associated with the delivery
of the proposed expansion at Brudenell Primary School. This
represents the tender sum provided by LBS and does not include the
package of previously agreed enabling works.
b. £111,013 for NPS fees for RIBA Stages One to Six.
c. £20,000 for loose furniture and equipment, based on an
increase per year of 20 pupils.
d. £5,574 for additional surveys and the Building Control
application.
e. A client held contingency commensurate with the complexity and
scale of the refurbishment and remodelling of the Brudenell Centre
for primary school usage. Includes for a risk allowance to
facilitate connection of the schools ICT network to the new
accommodation.
Wards Affected: Headingley;