Decision details

Tender Acceptance Report – Learning Places Expansion of Hawksworth Wood Primary School

Reference: D44610

Decision Maker: Director of Children and Families

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

The Chief Officer, Learning Improvement agreed to:

• Approve the request to award the contract for the sum of £603,027.51 to Pacy and Wheatley Construction to refurbish 5 classrooms, 2 toilets blocks, provide an additional toilet block and extend the kitchen to make it suitable for a 2 FE from September 2017 for the Learning Places Programme scheme at Hawksworth Wood Primary School.

• Authorise the signature of all contractual documentation with Pacy and Wheatley Construction in relation to the tender acceptance.

• Note the programme dates identified in section 4.0 of this report, in relation to the implementation of this decision.

• Note that the whole scheme will be completed in August 2018; however sufficient accommodation, through this summer works, will be available to accommodate the increased admission number from September 2017.

• Note that the Chief Officer, Projects, Programmes & Procurement Unit (PPPU) is responsible for scheme delivery.

Wards Affected: Kirkstall;

Contact: Anthony O'Connell, Project Manager 0113 3785895 Email: anthony.oconnell@leeds.gov.uk.

Publication date: 14/07/2017

Date of decision: 02/08/2017