Reference: D44669
Decision Maker: Director of Children and Families
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Head of Learning Systems agreed to:
1. authorise expenditure of £199,759 from capital scheme
number 32450/BGE/GRI to enable the delivery of the second and final
phase of construction works at Talbot primary school to support the
existing bulge cohort.
2. authorise acceptance of the tender submitted by the Leeds Local
Education Partnership in the sum of £167,902 including all
design and development fees.
3. note the programme dates identified in section 4.0 of the report
in relation to the implementation of this decision. The final
delivery date for this scheme is prior to the commencement of term
September 2107.
4. note that the officer responsible for implementation is the
Built Environment Principal Development Officer.
Wards Affected: Roundhay;
Contact: Edward Staveley, Principal Asset Management Officer , City Development 0113 3951403 Email: edward.staveley@leeds.gov.uk.
Publication date: 26/07/2017