Decision details

Design & Cost Report and Tender Acceptance for the Learning Places 2017 Bulge Cohort – Immaculate Heart of Mary Catholic Primary School (Phase 1) Capital Scheme Number: 32450/BGE/IHM

Reference: D44671

Decision Maker: Director of Children and Families

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

The Head of Learning Systems agreed to:

1. Authorise expenditure of £138,563.15 from capital scheme number 32450/BGE/IHM to allow Phase One of the ‘bulge’ cohort works at Immaculate Heart of Mary Catholic Primary School to commence over summer 2017. This works forms part of the Learning Places 2017 Bulge Cohort Programme.

2. Authorise acceptance of the tender submitted by Immaculate Heart of Mary Catholic Primary School in the sum of £106,464.50 for delivery of Phase One. This figure is inclusive of all fees and costs incurred directly by Immaculate Heart of Mary Catholic Primary School.

3. Note that the breakdown of project costs, highlighted in point 1 above, are detailed within section 5.5 of this report.

4. Note that this report refers to Phase One only, Phase Two will be subject to a separate programme and approvals report.

5. Note the programme dates identified in section 4.0 of this report in relation to the implementation of this decision. The final delivery date for this scheme is prior to the commencement of term September 2017.

6. Note that the officer responsible for implementation is the Head of Learning Systems, Children and Families.

Wards Affected: Moortown;

Contact: Christopher Gosling, Estate Management - Development Officer 0113 3787198 Email: christopher.gosling@leeds.gov.uk.

Publication date: 27/07/2017

Accompanying Documents: