Decision details

Highways England – M62 Junctions 27 /28 improvements - Section 6 Highways Act 1980 Agreement

Reference: D44773

Decision Maker: Director of City Development

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

The Head of Transportation:
i) approved the undertaking of the implementation of a scheme to improve the capacity of, and reduce congestion, at junctions 27 and 28 of the M62, as indicated on the attached drawings numbered B2005501-J27-0100-001, B2005501-J27-0100-002, B2005501-J28-0100-001, and B2005501-J28-0100-002; and

ii) entered into an agreement under the provisions of Section 6 of the Highways Act 1980 (attached at appendix A) to allow LCC and their contractor to undertake the works, as specified above, on the HE network.

Wards Affected: Ardsley and Robin Hood; Morley North; Morley South;

Contact: Sabby Khaira, Highways Officer 0113 3787375 Email: sabby.khaira@leeds.gov.uk.

Publication date: 05/09/2017

Accompanying Documents: