Reference: D57252
Decision Maker: Director of Strategy and Resources
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Digital and Information Officer approved the award of a contract for the facilities management for Council’s data centre environments in two lots where Lot 1 for the regular Planned Preventative Maintenance visits will be awarded solely to Sudlows Limited and Lot 2 will be awarded to Sudlows Limited, Keysource Limited and Stultz Modular Limited to use as a framework to bring more competition for goods and services. The contract has an estimated value of £100,000 per year for a period of 3 years with an option to extend for a further 12 months, commencing 1st May 2024.
Wards Affected: (All Wards);
Contact: Adam Edmands, Data Centre & Voice Team Manager 01133784303 Email: Adam.Edmands@leeds.gov.uk.
Publication date: 11/03/2024
Date of decision: 11/03/2024
Accompanying Documents: