Reference: D57268
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
That the Director of City Development approved
the Council entering into an Early Works Underwriting Agreement
(EWUA) with the Contractor and agreements for project manager and
quantity surveyor services during the early works up to the sum of
£500,000. This is due to urgent nature health and safety
implications of the Theatre repairs. The EWUA will enable the
Council to instruct the Contractor to commence the critical
enabling works required on the Theatre site ahead of the approval
of the Key Decision.
Wards Affected: Little London and Woodhouse;
Contact: James Anderson 0113 378 5960 Email: james.anderson@leeds.gov.uk.
Publication date: 14/03/2024
Accompanying Documents: