Reference: D41602
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation):
i) noted the contents of this report;
ii) approved the proposal at the total cost of £95,000;
and
iii) gave authority to incur expenditure of £87,000 works
costs and £8,000 staff costs, to be funded from the LTP
Transport Policy Capital Programme (100% Government grant
funding).
Wards Affected: Roundhay;
Contact: Richard Tallant, Highways Officer 0113 247 6760 Email: richard.tallant@leeds.gov.uk.
Publication date: 23/09/2014