Reference: D41957
Decision Maker: Director of Children's Services
Is Key decision?: Yes
Is subject to call in?: Yes
To approve the Design & Cost report for the project including the delivery programme budget and design.
The Director of Children’s Services agreed to:
· approve the design and cost report for the scheme at broadgate Primary School, the cost being £2.79 million with the appropriate details of the programme, design and cost as set out in this report; and
· note that the Chief Officer, Public Private Partnerships Unit & Procurement Unit is responsible for scheme delivery which will be implemented for the first phase by August 2015 and the final phase December 2015.
Reason Key: Expenditure > £250,000;
Wards Affected: Horsforth;
Other reasons / organisations consulted
Public consultation period from 25th November 2013 – 17th January 2014.
Consultees
Schools, early years, public, elected members, MPs, diocese.
Contact: Debra Penny, Project Coordinator, Built Environment 0113 3952451 Email: debra.penny@leeds.gov.uk.
Publication date: 07/01/2015
Date of decision: 15/01/2015
Effective from: 23/01/2015