Reference: D42157
Decision Maker: Director of Children's Services
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
To approve the Design and
Cost report for the project including the delivery programme budget
and design.
Decision:
The Director of Children’s
Services agreed to:
- approve the procurement strategy and
design and cost report for the scheme at Pudsey Primrose Primary
School, the cost being £2,719,430 with the appropriate
details of the programme, design and cost as set out in this
report;
- approve
an application to the Basic Need Programme Contingency fund for
£969,430 to enhance the previously agreed budget of
£1,750,000.
- agree the
procurement strategy as a quality initiated call-off using the
YORbuild framework in line with CPR
3.1.8. (CPRs 3.1.5 and 3.1.6 not applying as there are no exclusive
supplier arrangements or an ISP to undertake this work),
- agree that the project at Pudsey
Primrose Primary School to expand by 105 pupils changing it from a
1.5 Form Entry Primary School to a 2 Form Entry Primary School,
from September 2015, as part of the Primary Basic Need Programme,
can progress to the procurement phase, and
- note that
the Chief Officer, Public Private Partnerships Unit &
Procurement Unit is responsible for scheme delivery which will be
completed October 2015.
Reason Key: Expenditure > £250,000;
Wards Affected: Pudsey;
Other reasons / organisations consulted
Contact: Darren Dobson, Senior Technical Manager 0113 3950302 Email: darren.dobson@leeds.gov.uk.
Publication date: 18/03/2015
Date of decision: 26/03/2015
Effective from: 03/04/2015
Accompanying Documents: