Decision details
S278 Works Associated with the Development of a Motor Vehicle Dealership on Land at Gelderd Road and Ring Road Beeston, Leeds 12.
Reference: D42198
Decision Maker: Director of City Development
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Decision:
The Head of Engineering Services:
i) noted the highway works as outlined in Section 3.1 and indicated
on Leeds City Council Drawing Number EP/732186/MISC/02B at an
estimated cost of cost of £836,600;
ii) gave authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by this Council at the cost of the
developer;
iii) give authority to tender and implement the works as set out in
Section 3.1;
iv) approved an injection of £836,600 into the City
Development Capital Programme to be fully funded by the
developer;
v) gave authority to incur expenditure of £722,000 works
costs (this includes the estimated £6,000 cost of TRO works,
the authority to advertise the TRO will be the subject of a further
report) and £114,600 staff costs to be fully funded by a
section 278 developer contribution; and
vi) instructed the City Solicitor to advertise a draft Traffic
Regulation Order on Gelderd Road, as shown on drawing number
EP/732186/MISC/04 and, if no valid objections are received, to
make, seal and implement the Order as advertised.
Wards Affected: Beeston and Holbeck;
Contact: Neil Chamberlain, Highways Officer 0113 2475288 Email: neil.chamberlain@leeds.gov.uk.