Reference: D43342
Decision Maker: Director of Children's Services
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Head of Services, Learning Systems agreed
to:
* authorise further expenditure of up to £381,723.43 from
Capital Scheme Number 32274/GLE/000 noting a revised total early
works value of £745,168 (inclusive of £363,444.76
previously approved by the Head of Service, Learning Systems on 03
March 2016 under the original Early Works Agreement) to enable
additional early works to be carried out prior to the main contract
award for the proposed Learning Places expansion of Gledhow Primary
School; and
* approve entry into a revised Early Works Agreement with Wates
Construction Limited up to a maximum value of £745,168
(£363,444.76 previously approved as part of the original
Early Works Agreement plus £381,723.43 subject to approval
via this report).
Wards Affected: Roundhay;
Contact: Melanie Hibbert, Project Manager 07891 277092 Email: melanie.hibbert@leeds.gov.uk.
Publication date: 25/04/2016