50 New Generation Transport (NGT) Update PDF 106 KB
To consider the report of the Director of City Development on progress of the New Generation Transport proposals and how these fit strategically into a wider transport strategy for Leeds and the wider City Region.
Minutes:
The Director of City Development submitted a report on progress of the New Generation Transport proposals and how these fitted strategically into a wider transport strategy for Leeds and the wider City Region.
RESOLVED –
(a) That the report be noted and that the findings of the Strategic Fit work, identified in appendix 1 to the report be endorsed.
(b) That a capital programme injection of £1,400,000 and a transfer from scheme 99926 of £1,050,000 funded from Section 106 developer contributions be approved and that authority be given to spend of £2,450,000 as the Council’s contribution towards scheme development costs, to cover design fees and the preparation and consultation costs necessary to develop the work through to a Major Scheme Business Case submission.
(c) That a further progress report be brought to this Board once scheme development has progressed.