PROVISION OF NEW MODULAR CLASSROOM ACCOMMODATION AT BLENHEIM PRIMARY SCHOOL

Meeting: 20/06/2012 - Executive Board (Item 18)

18 Design and Cost Report - Blenheim Primary School Additional Accommodation pdf icon PDF 88 KB

To consider the report of the Director of Children’s Services seeking approval to proceed with works to provide additional accommodation at Blenheim Primary school

 

Additional documents:

Minutes:

The Director of Children’s Services submitted a report which sought approval to proceed with works which would provide additional accommodation at Blenheim Primary School. In addition, the report  sought the necessary authority to incur expenditure of £643,984 on phase 2 of the scheme.

 

RESOLVED –

(a)  That the additional accommodation works at Blenheim Primary School, at an estimated total cost of £643,984, be approved.

 

(b)  That expenditure of £643,984 from capital scheme number 15822\BLE\000 be authorised.