Issue - meetings

Design and Cost Report for Lane End Basic Need Project 2014

Meeting: 14/02/2014 - Executive Board (Item 185)

185 Design and Cost Report for Lane End Primary School Basic Need Project pdf icon PDF 210 KB

To consider the report of the Director of Childrens Services providing information regarding the Basic Need scheme to construct the new Lane End Primary School. In addition, the report seeks authority to incur capital expenditure of £7,205,100 in order to undertake the works required to provide accommodation to support a new 2FE primary school with 26 place nursery and associated external facilities.

 

Additional documents:

Minutes:

The Director of Children’s Services submitted a report providing information regarding the Basic Need scheme to construct the new Lane End Primary School. Specifically, the report sought authority to incur capital expenditure of £7,205,100 in order to undertake the works required to provide accommodation to support a new 2FE primary school with 26 place nursery and associated external facilities.

 

RESOLVED –

(a)  That expenditure of £7,205,100 be authorised from capital scheme number 16585/SLE/000 in order to enable the construction of the new Lane End Primary School.

 

(b)  That the programme dates identified within section 4.0 of the submitted report in relation to the implementation of the related decisions, be noted. It also be noted that the final delivery date for total completion of the scheme is September 2015.

 

(c)  That it be noted that the Director of Children’s Services is responsible for implementation of such matters.