Issue - meetings

Leeds 2023 European Capital of Culture Delivery Budget

Meeting: 17/07/2017 - Executive Board (Item 35)

35 Leeds 2023 European Capital of Culture Bid Interim Report pdf icon PDF 72 KB

To consider the report of the Director of City Development providing an interim report on the work being undertaken towards the preparation of a Leeds bid for European Capital of Culture 2023 and which seeks approval for the associated recommendations, as detailed.

 

(Please Note: Appendix 1 to this report is designated as exempt from publication under the provisions of Access to Information Procedure Rule 10.4(3))

Additional documents:

Minutes:

Further to Minute No. 137, 8th February 2017, the Director of City Development submitted a report providing an update on the work being undertaken towards the preparation of a Leeds bid for European Capital of Culture 2023 and which sought approval for the associated recommendations, as detailed.

 

Members welcomed the proposals detailed within the submitted report and noted that the deadline for initial bid submissions was 27th October 2017.

 

Following consideration of Appendix 1 to the submitted report designated as exempt from publication under the provisions of Access to information Procedure Rule 10.4(3), which were considered in private at the conclusion of the meeting, it was

 

RESOLVED –

(a)  That the overall progress made over the past twelve months, be noted;

(b)  That the incorporation of Leeds Culture Trust be noted, and that the process goingforward of developing appropriate governance structures, be approved;

(c)  That the budget proposals, as detailed within exempt appendix 1 to the submitted report, for the delivery of EuropeanCapital of Culture in 2023, be approved;

(d)  That officers be requested to return to Executive Board in October 2017 with the full and final detailed bid in advance ofthe deadline for the first stage submission of 27th October 2017;

(e)  That it be noted that should Leeds be shortlisted, then a second and final application will need tobe submitted by mid-2018.