Issue - decisions

Tender Acceptance Report - Basic Need - East Ardsley Primary School Capital Scheme Number: 16585/ETA/PH3

29/09/2014 - Tender Acceptance Report - Basic Need - East Ardsley Primary School Capital Scheme Number: 16585/ETA/PH3

The Deputy Director, Children's Sercies (Learning, Skills & Universal Services) agreed to:
* approve the request to award the contract in the sum of £526,774.40 to QED for the Basic Need new build expansion of East Ardsley Primary School;
* authorise the signature of the deed of variation of the Project Agreement required to implement this scheme;
* authorise the signature of the independent certifiers' deed of appointment and collateral warranties with the main building contractor, architect and structural engineer; and
* authorise the signature of all other documentation that is required to deliver the project in the opinion of the Programme Manager, Built Environment.