The Built Environment Programme Manager agreed to:

i.Approve the proposal to carry out essential kitchen improvement works to address urgent health and safety issues at Talbot Primary School.

ii.Approve the procurement strategy to utilise competitive tendering methods in accordance with CPR 3.1.8.

iii.Authorise expenditure in the sum of £142,932.00 from capital scheme number 32014/EXP/TAL ‘Universal Infant Free School Meals’ (UIFSM) to enable the proposed works at Talbot Primary School.

iv.Note that the Asset Management Planning Manager (Built Environment Team) is responsible for scheme delivery which will be completed by September 2015.