Design & Cost Report for the Basic Need Bulge Cohort - Gledhow Primary School Capital Scheme Number: 16981/BGE/GPS

23/06/2015 - Design & Cost Report for the Basic Need Bulge Cohort - Gledhow Primary School Capital Scheme Number: 16981/BGE/GPS

The Programme Manager, Built Environment agreed to:
* authorise expenditure of £229,718 from capital scheme number 16981/BGE/GPS to enable the installation of temporary modular accommodation, including any necessary ancillary works, at Gledhow Primary School;
* note the programme dates identified in section 4.2 of the attached report in relation to the implementation of this decision. The final delivery date for this scheme is prior to the commencement of term September 2015; and
* note that the officer responsible for implementation is the Built Environment Principal Development Officer.