DEsign & Cost Report for the Basic Need Bulge Cohort - St Philip's Catholic Primary & Nursery School Capital Scheme Number: 16981/BGE/MSP

23/06/2015 - DEsign & Cost Report for the Basic Need Bulge Cohort - St Philip's Catholic Primary & Nursery School Capital Scheme Number: 16981/BGE/MSP

The Programme Manager, Built Environment agreed to:
* Authorise expenditure of £124,542 from capital scheme number 16981/BGE/MSP to enable the installation of temporary modular accommodation, including any necessary ancillary works, at St Philip's Catholic Primary & Nursery School;
* note the programme dates identified in section 4.2 of the attached report in relation to implementation of this decision. The final delivery date for this scheme is prior to the commencement of term September 2015; and
* note that the officer responsible for implementation is the Built Environment Principal Development Officer