The Built Environment Programme Manager agreed to:
* authorise expenditure of £166,629 from capital scheme number 16981/BGE/RPS to enable the proposed works at Raynville Primary School;
* note the programme dates identified in section 4.2 of the attached report on relation to the implementation of the decision. The final delivery date fo rhtis scheme is September 2015; and
* note that the officer responsible for implementation is the Built Environment Principal Development Officer.