Design & Cost Report for the Basic Need 2015 Bulge Cohort - Bramley Primary & Scholes Primary School modular unit relocation. Capital Scheme Number: 16981/BGE/BSC

26/06/2015 - Design & Cost Report for the Basic Need 2015 Bulge Cohort - Bramley Primary & Scholes Primary School modular unit relocation. Capital Scheme Number: 16981/BGE/BSC

The Programme Manager, Built Environment authorised expenditure of £232,233 from capital scheme number 16981/BGE/BSC to enable the relocation of two existing double classroom modular buildings, ownded by rthe Authority and currently in use on a temporary basis as St. Oswald's and Little London Primary Schools, to Bramley Primary School and Scholes (Elmet) Primary School. This includes any works associated with siting these buildings on the aforementioned sites.